防水涂料施工方法
防水涂料施工方法、工艺及技术措施。
Construction method, technology and technical measures of waterproof coating.
本工程地下室底板,地下室外墙防水层两道。采用2㎜厚聚氨脂防水涂料,卷材采用三元乙丙橡胶防水卷材1.5㎜厚。
There are two waterproofing layers for basement floor and basement exterior wall of this project. A 2-inch thick polyurethane waterproofing coating was used, and EPDM waterproofing membrane was 1.5 inch thick.
1. 地下防水工程的防水层,均应在地基及结构验收合格后施工。
1. The waterproofing layer of underground waterproofing engineering shall be constructed after the foundation and structure have passed the acceptance.
2. 地下室底板防水工程施工期间,地下水位应降至防水工程底部最低标高以下,不小于300㎜,直至防水工程全部完成为止。
2. During the construction of basement floor waterproofing project, the groundwater level should be reduced to below the lowest elevation of the bottom of the waterproofing project, not less than 300 feet, until the completion of the waterproofing project.
3. 聚氨脂防水涂料施工、工艺及方法
3. Construction, Technology and Method of Polyurethane Waterproof Coatings
防水涂料施工工艺
Construction Technology of Waterproof Coatings
施工顺序:基层处理 涂刷底层涂料 涂布第一道涂膜防水层 涂布面涂膜防水层 质量检查验收合格 进行下道工序卷材施工。
Construction sequence: Base treatment, brushing the bottom coating, coating the first film waterproof layer, coating the surface waterproof layer quality inspection and acceptance of qualified coil construction in the next process.
施工前应检查,基层要坚实具有一定强度,表面无浮土砂粒等污染物。基层应干燥,含水率应少于9%为宜。
Before construction, it should be checked that the base should be firm and have a certain strength, and the surface should be free of pollutants such as floating soil and sand grains. The base should be dry and the moisture content should be less than 9%.
涂布顺序应先垂直面,后水平面,先阴阳角及细部后大面每层涂布方向应顺直。
The coating sequence should be vertical first, then horizontal. The direction of each coating layer should be straight from the Yin-Yang angle and the detail to the large surface.